Erection and Commissioning |
|
| |
|
| |
Total established power of hydroelectric power plants built and commissioned by TEMSAN so far is 702,605 MW. Those HEPP’s are Kepez II, Manavgat, İvriz, Hoşap, Tercan, Koçköprü, Kralkızı, Dicle, Kuzgun, Çamlıgöze, Suatuğurlu, Beyköy, Batman, Mercan and Kürtün which are fifteen.
Those power plants, whose annual average electricity energy production is 1.846 Million kWh/year, make a contribution of 92,3 Million USD to national economy.
Manufacture, erection, test and commissioning works of a/m mentioned HEPP have been realized by TEMSAN's staff.
|
| |
REALISED PROJECTS |
| |
|
Project
Name |
Turbine Type |
Power
MVA |
Annual
Generation
(GWh) |
Contribution to National Economy
(USD) |
Exchange
Substitution
(USD) |
Comm.
Date |
Location |
1 |
KEPEZ II HEPP |
Kaplan (Pipe Type) |
2x3.45 |
21 |
1,050,000 |
1,050,000 |
1986 |
ANTALYA |
2 |
İVRİZ HEPP |
Horizontal Francis |
2x0.61 |
4 |
200,000 |
200,000 |
1986 |
EREĞLİ-KONYA |
3 |
MANAVGAT HEPP |
Revision |
2x32 |
220 |
11,000,000 |
11,000,000 |
1986 |
ANTALYA |
4 |
HOŞAP HEPP |
Horizontal Francis |
2x2.25 |
13 |
650,000 |
650,000 |
1989 |
VAN |
5 |
TERCAN HEPP |
Vertical Francis |
3x5.50 |
51 |
2,550,000 |
2,550,000 |
1990 |
ERZİNCAN |
6 |
KOÇKÖPRÜ HEPP |
Horizontal Francis |
4x2.65 |
44 |
2,200,000 |
2,200,000 |
1994 |
VAN |
7 |
KRALKIZI
HEPP |
Vertical Francis |
2x52 |
146 |
7,300,000 |
7,300,000 |
1998 |
DİYARBAKIR |
8 |
KUZGUN
HEPP |
Vertical Francis-Horizontal Francis |
3x7.5+1x2.5 |
36 |
1,800,000 |
1,800,000 |
2000 |
ERZURUM |
9 |
DİCLE
HEPP |
Vertical Francis |
2x65 |
298 |
14,900,000 |
14,900,000 |
2000 |
DİYARBAKIR |
10 |
ÇAMLIGÖZE HEPP |
Vertical Kaplan |
2x19 |
102 |
5,100,000 |
5,100,000 |
2000 |
SİVAS |
11 |
BEYKÖY
HEPP |
Vertical Kaplan |
3x6.00 |
87 |
4,350,000 |
4,350,000 |
2001 |
ESKİŞEHİR |
12 |
SUATUĞURLU HEPP |
Vertical Kaplan |
1x25.5 |
78 |
3,900,000 |
3,900,000 |
2001 |
SAMSUN |
13 |
BATMAN
HEPP |
Vertical Francis + Horizontal Francis |
3x75.5+1x7 |
483 |
24,150,000 |
24,150,000 |
2003 |
BATMAN |
14 |
MERCAN
HEPP |
Vertical Francis |
3x7.5 |
78 |
3,900,000 |
3,900,000 |
2003 |
TUNCELİ |
15 |
KÜRTÜN
HEPP |
Vertical Francis |
2x46 |
198 |
9,900,000 |
9,900,000 |
2003 |
GÜMÜŞHANE |
|
TOTAL |
|
791.22 |
1,859 |
92,950,000 |
81,950,000 |
|
|
|
| |
HEPP PROJECT UNDER CONSTRUCTION |
|
| |
|
Project
Name |
Turbine Type |
Power
MVA |
Annual
Generation
(GWh) |
Contribution to National Economy
(USD) |
Exchange
Substitution
(USD) |
Comm.
Date |
Location |
1 |
ALPASLAN-I HEPP |
Vertical Francis |
4x45 |
488 |
24.400.000 |
24.400.000 |
2007 |
MUŞ |
2 |
ÇİNE HEPP |
Vertical Francis |
2x27.5 |
118 |
5.900.000 |
5.900.000 |
2007 |
AYDIN |
3 |
KILAVUZLU HEPP |
Vertical Francis |
4x15.9 |
100 |
5.000.000 |
5.000.000 |
2007 |
K.MARAŞ |
4 |
MANYAS HEPP |
Vertical Francis |
3x7.65 |
59 |
2.950.000 |
2.950.000 |
2008 |
BALIKESİR |
5 |
TOPÇAM HEPP |
Vertical Francis |
3x23.5 |
200 |
10.000.000 |
10.000.000 |
2009 |
ORDU |
|
TOTAL |
|
392.05 |
965 |
40.300.000 |
48.250.000 |
|
|
|
|
|
|
| |
|