Generator Tests |
|
|
Measurement of Stator Winding Resistance |
|
|
Withsand Tests for Stator Winding Insulation |
|
|
DC Resistance Measurement of Stator Winding |
|
|
Stator Winding Insulation Tests |
|
|
Stator Care Temperature Rise and Fe Loss Measurement |
|
|
Rotor Pole Insulation Resistance Measurement |
|
|
Rotor Pole Insulation Withsand Test |
|
|
Rotor Pole DC Resistance Measurement |
|
|
Rotor Pole Insulation Test |
|
|
Rotor Balance |
|
|
Drying of Generator Windings |
|
|
Measurement of Generator Open-Circuit Characteristics |
|
|
Measurement of Generator Short-Circuit Characteristics |
|
|
Generator V-curve Measurement |
|
|
Generator Impedance Measurement |
|
| |
|
|
| |
Balance |
|
|
Unbalance elimination of material weighs from 200 to 45000 kg (runner,shaft,rotor,flywheel,etc.) in our Factory. |
|
|
Local determination and elimination works for comlete rotating systems. |
|
|
Local control for concentricity and allignment of complete shaft installation. |
|
| |
|
|
| |
Other Tests |
|
|
Pressure tests for hydraulic systems |
|
|
Measurement,analyze and elimination of vibration |
|
|
Measurement and evaluation of insulationand impedance |
|
|
High Voltage withstand test (50kV AC - 120 kV DC) |
|
|
Lightning impulse withstand test. (30kVp) |
|
|
Insulation oil test and measurement of viscosity |
|
|
Destructive Tests (DT) |
|
| |
 Tensile |
|
| |
 Yield |
|
| |
 Notched |
|
| |
 Hardness |
|
|
Non Destructive Tests (NDT) |
|
| |
 Ultrasonic |
|
| |
 Magnetic |
|
| |
 Examination and analyze of penetrant painting
|
|
| |
|
|
| |
|
|